Timeline
Plans & permitting can take 4-8 weeks depending on location. Below starts once approved permits acquired.
Phase 1
Demo
Excavation (~2 days)
Plumbing (trenching)
Steel
Electrical
Pre Gunite Inspection
Phase 2
Gunite
Tile
Set up Concrete Decking and Drainage
Deck Inspection (Permission Letter Required)
Phase 3
Concrete deck pour
Equipment Installation
Door Alarms Installed
Pre Plaster Inspection (Home owner has to be home)
Phase 4
Strip Concrete Forms & Clean up
Pebble/Plaster Interior Installation (Final Payment Due)
Acid wash - The pool is filled with water day after pebble installation (2 day process)
Phase 5
Orientation / Pool School - delivery/installation of pool sweep
Final Inspection (Home owner has to be home)
Inspectors will not enter backyard if there is not a signed letter allowing permission. Most pool projects are completed within 6 to 8 weeks, more customized or elaborate designs may take between 8 to 12 weeks to finish.